<< Click to Display Table of Contents >> Navigation: Modules > Workflow Automation > Project Calendars > Holidays |
A holiday may be added to the project calendar using the following steps:
1.Position the calendar to the date of the holiday.
2.Enter a description for the holiday in the Holiday Description box.
3.Click Set.
A holiday may be removed from the project calendar using the following steps:
1.Position the calendar to the date of the holiday or click on the holiday from the Holidays this year list.
2.Click Remove in the Holidays this year area.
NOTE: Only the user who initially created a holiday, or any person with administrative level access (10), may remove it.